A few updates for you regarding facade work outside:
1. Work has been completed on drops 1-3 - see diagram below on the northeast corner of 35th and 77th st.
2. Starting today, Amsterdam will be moving the scaffolding from L/M lines to J/K/L lines on 77th st. Residents should keep windows closed and locked, blinds/curtains drawn during work hours. Remove items on walls that could be damaged by vibrations. Amsterdam Warwick Owners Corp. and New Bedford are not responsible for damages.
3. Tomorrow starting around 10:30 water tests will be conducted on the higher floors of "J" and "O" lines. "Downpour" conditions will be created for several hours with a hose - for "J" and "O" owners on all floors please keep your windows shut tight.
4. Last night we had heavy rains, please continue to report new leaks along exterior walls to Orlando - bubbling paint, stained walls/ceilings, dampness are some examples. This is very helpful to capture all work areas while our engineering team and contractors are on site.